REVIEW OF RESEARCH METHODS IN CONCESSION PERIOD FOR PUBLIC PRIVATE PARTNERSHIP

A Suryaningrum[1]*,3, C Utomo1, E Santoso2

 

1 Department of Civil Engineering, Institut Teknologi Sepuluh Nopember, Indonesia

2 Department of Urban Regional Planning Engineering, Institut Teknologi Sepuluh Nopember, Indonesia

3 Study Program of Civil Engineering, Universitas Bhayangkara, Surabaya

[1]* Corresponding author’s email: [email protected]

DOI: https://doi.org/10.20885/icsbe.vol2.art16

 

ABSTRACT

Public Private Partnership (PPP) needs to be developed, related to the construction of infrastructure projects that require large costs incurred by the government. One of the important variables in preparing PPP contracts is to determine the concession period by taking into account the risks and uncertainties that occur during the concession period. The purpose of the study is to find out the research methods used related to the concession period by analyzing 30 papers related to the concession period. In the collection of research data, there are quantitative and qualitative approaches. The methods used in each study use different methods, based on the analysis of research methods from 30 papers. In the topic of discussion of the concession period, in general, the paper discusses the type of modeling, decision criteria, solutions, cases, research objects, risks and uncertainties and methods used. Previous studies related to the concession period have many different methods and objectives, In quadrant mapping shows that the use of quantitative methods with secondary data is the most dominant. Based on the reviews that have been carried out in this study, it can be concluded that the use of quantitative methods with secondary data is the most dominant.

 

Keywords: Public private partnership, research methods, concession period

 

REFERENCES

Zou W, Kumaraswamy M, Chung J and Wong J 2014  Int. J. Proj. Manag. 32(2) 265-274.

Feng K, Wang S Q, Chunlin Wu, Guangtao Xia, Wangyin Hu 2019 Eng. Econ. 30(1) 24–31

Carbonara N, Costantino N, Pellegrino R 2014 Int. J. Proj. Manag. 32  1223–1232

Khanzadi M, Nasirzadeh F, Alipour M 2010 Conf: Information Financial Eng. (ICIFE) IEEE International  978-1-4244-6928-4

Ullah F, Ayub B, Siddiqui S Q and Muhammad Jamaluddin Thaheem M J 2016 J. Financial Manag. Prop. and Constr. 21(3) 269 – 300

Hadi A H, Erzaij K R 2019 Civ. Eng. J. 5(6)

Nasirzadeh F, Khanzadi M, Alipour M 2014 Iran. J. of Manag. Stud. (IJMS)  7(2) 423- 442

Ullah F 2015 Const. Eng. Manage.

Pivatto D, Fernandez R N, Saulo H, Carraro A 2017 Int. J. Econ Finance. 9(12)

Xu Y, Peng Y, Qian Q K,  Chan A P, 2015 Sustainability. 7(5) 5720-5734

Bagui S K and Ghosh A  2013 Jordan. J. Civ. Eng.  7(4)

Bao H, Peng Y, Ablanedo-Rosas J H, Gao H 2015 Int. J. Project Manage. 33 1151–1159

Jin H, Shijing Liu, Liu C, Udawatta N 2019 Eng. Constr. Archit. Manage 26(10) 2347-2363

Elbaz M M, Adel I. Eldosouky A  I 2019 Eng. Res. J. (ERJ) 3

Nur Dzikri Huda N D,  and Ahmad Danu Prasetyo A D 2020 Eur. J. Business Manage. Res.  5(4)

Wang Z, Tan H, Wang J and Hu C 2015 Math. Probl. Eng. (2015)

Feng K, Wang S, Li N,  Wu C and Xiong W 2018 J. Civ. Eng. Manage. 24(2) 116–129

Ma G, Du Q  and Wang K 2018 Sustainability 10(3) 706.1-706.21

Xiong W, Zhang X 2014 J. Constr. Eng. Manage. 140(5)

Zhang X, Haijun Ba, Wang H, Skitmore M 2016 Int. J. Project Manage. 34 523–532

Nguyen N, Almairi K and Boussbaine  H 2020 Built Environ. Proj. Asset Manag.  11(1) 4-21.

Bagui S K, Ghosh A 2013  Jordan. J. Civ. Eng 7(4)

Yan X, Chong H, Zhou J, Li Q 2019 J. Civ. Eng. Manage. 25(3) 265–275

Hu H,  Zhu Y 2014 J. Constr. Eng. Manage. 141(1)

Xu Y, Skibniewski M, Zhang Y, Chan  APC and Yeung JFY 2012 Int. J. Strateg. Prop. Manag. 16(2) 201–217

Zh Y, Xu F., Hu H 2016 Journal of Shanghai Jiaotong University (Science) 21(3) 320-327

Zhang Y, Yuan J, Zhao J, Cheng L and Li Q (2022)  J. Constr. Eng. Manage. 148(2)

Vorasing P, Phommasone S 2015 PSAKUIJIR 4(2)

Liu S, Jin H, Xie B, Liu C, Mills A 2018 Int. J. Strateg. Prop. Manag. 22(5) 424–435

Blank FF, Samanez CP, Baidya TKN, Dias MAG 2016 Production 26(1) 39-53

Song J, Song D, Zhang D 2015 J. Constr. Eng. Manage.14(10)